GE wind farm in Baleni, Galati County

GE wind farm in Baleni, Galati CountyGeneral Electric, the American engineering company who is also operating in Romania, has announced yesterday that they have finished the commissioning for a 50 MW wind plant in Baleni, Galati County.

The project is about installing 20 GE 2.5-103 wind turbines, 2.5 MW capacity each.

Furthermore, GE agreed with GDF Suez Energy Romania, the developer of the project, also to supply maintenance and service work for the following ten years, monitoring the installation using special GE systems.

According to project data, the wind park will generate enough energy to cover the necessary for 50.000 homes.